Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp
CountyRAINS
HighwayUS0069
From0.001
ToRAINS COUNTY
CSJ6434-12-001
Proj IDMMC - 643412001
Work TypeEMULSION
0.010273750.00120509.38100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-23
Work Completed05-18-24
Time Computed00-00-00
Contract Working Days182
Addl Days Granted182
Working Days Charged362
Percent Time Used99
Contractor(s)
SUBCONTRACTOR(S) FOR CCSJ: 6434-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234216
Totals273750.000.00120509.38100.0
CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6434-84-001
Proj IDRMC - 643484001
Work TypeILLUMINATION MAINTENANCE
0.010439885.3096422.5021.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged128
Percent Time Used50
Contractor(s)
YUNEX LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234035
Totals439885.306527.2096422.5021.9
CountyLAMAR
HighwayUS0082
From0.001
ToPARIS DISTRICT
CSJ6435-78-001
Proj IDMMC - 643578001
Work TypeFLEXIBLE BASE
0.0101533000.00754533.2049.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted244
Working Days Charged336
Percent Time Used92
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6435-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234023
Totals1533000.000.00754533.2049.2
CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6440-51-001
Proj IDRMC - 644051001
Work TypeFULL DEPTH CONCRETE REPAIR
0.0102947460.001048014.2235.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-29-24
Work Completed
Time Computed00-00-00
Contract Working Days138
Addl Days Granted0
Working Days Charged33
Percent Time Used23
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234032
Totals2947460.00245816.101048014.2235.5
CountyGRAYSON
HighwayUS0069
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6441-62-001
Proj IDRMC - 644162001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
0.0104219509.821105754.5226.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged185
Percent Time Used72
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 6441-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234623
Totals4219509.82204897.641105754.5226.2
CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToHUNT, RAINS, HOPKINS, AND FRANKLIN CO.
CSJ6441-97-001
Proj IDRMC - 644197001
Work TypeMETAL BEAM GUARD FENCE REPAIR
0.010719833.00426388.0059.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged274
Percent Time Used75
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6441-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234209
Totals719833.0067940.00426388.0059.2
CountyLAMAR
HighwayFM0137
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6443-16-001
Proj IDRMC - 644316001
Work TypeMILL AND INLAY
0.0106031608.552911676.1148.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-06-23
Work Completed
Time Computed00-00-00
Contract Working Days114
Addl Days Granted0
Working Days Charged81
Percent Time Used71
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6443-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234425
Totals6031608.5541891.302911676.1148.2
CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS
ToPARIS DISTRICT
CSJ6445-19-001
Proj IDMMC - 644519001
Work TypeDE-ICING SALT
0.010891158.0086829.239.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-18-23
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted182
Working Days Charged257
Percent Time Used70
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234033
Totals891158.000.0086829.239.7
CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6445-37-001
Proj IDRMC - 644537001
Work TypeRAISED PAVEMENT MARKERS
0.010536512.0033137.006.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-26-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged96
Percent Time Used26
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234036
Totals536512.000.0033137.006.1
CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS
ToIN HOPKINS AND FRANKLIN COUNTIES
CSJ6446-04-001
Proj IDMMC - 644604001
Work TypeLIMESTONE ROCK ASPHALT
0.010525765.0090673.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-23
Work Completed05-28-24
Time Computed00-00-00
Contract Working Days120
Addl Days Granted120
Working Days Charged240
Percent Time Used100
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234034
Totals525765.000.0090673.88100.0
CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS
ToIN HUNT & RAINS COUNTIES
CSJ6447-08-001
Proj IDMMC - 644708001
Work TypeLIMESTONE ROCK ASPHALT
0.010412862.50333417.77100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-23
Work Completed05-27-24
Time Computed00-00-00
Contract Working Days120
Addl Days Granted120
Working Days Charged239
Percent Time Used99
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6447-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234224
Totals412862.500.00333417.77100.0
CountyHUNT
HighwayUS0069
FromVARIOUS LOCATIONS
ToIN HUNT & RAINS COUNTIES
CSJ6447-22-001
Proj IDMMC - 644722001
Work TypeDENSE GRADED HOT MIX
0.010439560.0045597.0210.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-11-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged234
Percent Time Used65
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6447-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234225
Totals439560.000.0045597.0210.3
CountyHOPKINS
HighwaySH0011
FromVARIOUS LOCATIONS IN THE
ToPARIS DISTRICT
CSJ6447-67-001
Proj IDMMC - 644767001
Work TypeDE-ICING SALT
0.010329771.8034554.0510.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted182
Working Days Charged244
Percent Time Used67
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6447-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234226
Totals329771.800.0034554.0510.4
CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN THE
ToPARIS DISTRICT
CSJ6447-73-001
Proj IDMMC - 644773001
Work TypeAGGREGATE
0.0102055511.00525740.7825.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-27-23
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted182
Working Days Charged218
Percent Time Used59
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6447-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234218
Totals2055511.0038438.99525740.7825.5
CountyGRAYSON
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToGRAYSON AND FANNIN COUNTY
CSJ6449-31-001
Proj IDRMC - 644931001
Work TypeMETAL BEAM GUARD FENCE REPAIR
0.010548277.50117984.3821.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6449-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234216
Totals548277.5043080.50117984.3821.5
CountyFANNIN
HighwayUS0082
FromVARIOUS LOCATIONS
ToIN FANNIN COUNTY
CSJ6450-35-001
Proj IDRMC - 645035001
Work TypeTRAFFIC CONTROL SERVICES
0.010599901.00272105.9045.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged213
Percent Time Used29
Contractor(s)
RHINO EQUITY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234031
Totals599901.0046985.00272105.9045.3
CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN THE
ToPARIS DISTRICT
CSJ6452-07-001
Proj IDMMC - 645207001
Work TypeROCK/RIPRAP
0.010582000.0052361.408.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted182
Working Days Charged183
Percent Time Used50
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6452-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234022
Totals582000.000.0052361.408.9
CountyRED RIVER
HighwayFM1701
FromVARIOUS LOCATIONS IN
ToRED RIVER AND LAMAR CO.
CSJ6453-47-001
Proj IDRMC - 645347001
Work TypeCROSS DRAINAGE STRUCTURE REPAIR
0.010853971.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RB CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244005
Totals853971.000.000.000.0
CountyHOPKINS
HighwaySH0019
FromVARIOUS LOCATIONS IN
ToHOPKINS AND FRANKLIN COUNTIES
CSJ6454-53-001
Proj IDRMC - 645453001
Work TypeTRAFFIC CONTROL SERVICES
0.0101246000.00424990.0034.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234217
Totals1246000.0099817.50424990.0034.1
CountyLAMAR
HighwayBU0271B
FromVARIOUS LOCATIONS IN THE
ToPARIS DISTRICT
CSJ6455-77-001
Proj IDMMC - 645577001
Work TypeHOT-MIX COLD-LAID
0.0101525575.00493727.6132.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-11-24
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted0
Working Days Charged142
Percent Time Used78
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6455-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234025
Totals1525575.000.00493727.6132.3

page 1 | page 2 | page 3 | page 4

Copyright 2022 • Texas Department of Transportation • All Rights Reserved • DisclaimerAccessibility
125 East 11th Street • Austin, Texas 78701

Monthly State Let Maintenance Report For Paris District As Of Jun 10, 2024 Page 2 Of 4 (2024)
Top Articles
Latest Posts
Article information

Author: Catherine Tremblay

Last Updated:

Views: 6343

Rating: 4.7 / 5 (47 voted)

Reviews: 94% of readers found this page helpful

Author information

Name: Catherine Tremblay

Birthday: 1999-09-23

Address: Suite 461 73643 Sherril Loaf, Dickinsonland, AZ 47941-2379

Phone: +2678139151039

Job: International Administration Supervisor

Hobby: Dowsing, Snowboarding, Rowing, Beekeeping, Calligraphy, Shooting, Air sports

Introduction: My name is Catherine Tremblay, I am a precious, perfect, tasty, enthusiastic, inexpensive, vast, kind person who loves writing and wants to share my knowledge and understanding with you.